piSaaS Customer Instances - Upgrading To The Latest Dashboard Version
When customers invest in taking a hosted piSaaS instance with us, we ensure that their hosted instances continue to be updated with the very latest dashboard product releases.
We perform piSaaS updates on a month basis, using the following process;
A dashboard product release is made available by the Panintelligence Quality Assurance team, which can be obtained by all customers as required - Software Download Repositories
The Panintelligence Service Acceptance team take a copy of the new dashboard product release, and perform a series of Service Acceptance tests against the piSaaS Platform (where customer instances are hosted). These checks are to ensure that the piSaaS platform and the software are fully compatible with one another and to ensure that an upgrade to the latest dashboard will not cause any service outages for our customers. This process typically takes 2 weeks to complete - including time for our Change Management processes.
Once the Service Acceptance checks have been approved through our Change Management processes, we finalise arrangements with our piSaaS customers to proceed
Customers will be notified of our intention to upgrade their instance with 48 hours’ notice of doing so.
Should they wish to opt out of the upgrade, we must be informed of this by 1pm on the day of the planned upgrade or sooner.
If the upgrade is not performed during the planed date/time, we will need to replan the activity, and a new date will need to be confirmed. A postponement could mean an upgrade is not possible until the follow months cycle.
Should no confirmation be received from the customer, we will work on the assumption to proceed with the upgrade, and update the instances as intended on the date/time outlined in the original notification
The Panintelligence team will then perform the planned upgrade and a confirmation notification of the success of the upgrade will be provided to the customer.
piSaaS Customer Upgrade Schedule
Month | Product Release | Slot 1 | Slot 2 |
---|---|---|---|
January 24 | No Release | - | - |
February 24 | 2024_01 | Feb 7, 2024 (AM) | Feb 8, 2024 (AM) |
March 24 | 2024_02 | Mar 13, 2024 (AM) | Mar 14, 2024 (AM) |
April 24 | 2024_03 | Apr 17, 2024 (AM) | Apr 18, 2024 (AM) |
May 24 | 2024_04 | May 8, 2024 (AM) | May 9, 2024 (AM) |
June 24 | 2024_05 | Jun 11, 2024 (AM) | Jun 11, 2024 (PM) |
July 24 | 2024_06 | Jul 10, 2024 (PM) | Jul 11, 2024 (AM) |
August | 2024_07 | Aug 7, 2024 (PM) | Aug 8, 2024 (AM) |
September 24 | 2024_08 | Sep 11, 2024 (PM) | Sep 12, 2024 (AM) |
October 24* | 2024_09 | N/A | N/A |
November 24 | 2024_11 | Dec 4, 2024 (PM) | Dec 5, 2024 (AM) |
December 24 | No Release | No Release | No Release |
January 25 | 2025_01 | Feb 5, 2025 (PM) | Feb 6, 2025 (AM) |
*additional time has been needed to complete the September 24 release items, therefore upgrades will proceed to the following month.