When customers invest in taking a hosted piSaaS instance with us, we want to ensure that their hosted instance continues instances continue to be updated with the very latest dashboard product releases.

We therefore aim to perform hosted customer piSaaS updates on a month basis.The manner by which we handle this process is, using the following process;

  1. A dashboard product release is made available by the Panintelligence Quality Assurance team, which can be obtained by all customers as required - Software Download Repositories

  2. The Panintelligence Service Acceptance team take a copy of the new dashboard product release, and perform a series of Service Acceptance tests against the piSaaS Platform (where customer instances are hosted). These checks are to ensure that the piSaaS platform and the software are fully compatible with one another and to ensure that an upgrade to the latest dashboard will not cause any service outages for our customers. This process typically takes 2 weeks to complete - including time for our Change Management processes.

  3. Once the Service Acceptance checks have been approved through our Change Management processes, we finalise arrangements with our piSaaS customers to proceed

  4. Customers will be notified of our intention to upgrade their instance with 48 hours’ notice of doing so.

  5. Should they wish to opt out of the upgrade, we must be informed of this by 1pm on the day of the planned upgrade or sooner.

  6. If the upgrade is not performed during the planed date/time, we will need to replan the activity, and a new date will need to be confirmed and . A postponement could mean an upgrade is not possible until the follow months cycle.

  7. Should no confirmation be received from the customer, we will work on the assumption to proceed with the upgrade, and update the instance instances as intended on the date/time outlined in the original notification

  8. The Panintelligence team will then perform the planned upgrade and a confirmation notification of the success of the upgrade will be provided to the customer.

Panel
bgColor#DEEBFF

piSaaS Customer Upgrade Schedule

Month

Product Release

Slot 1

Slot 2

January 24

No Release

-

-

February 24

2024_01

(AM)

(AM)

March 24

2024_02

(AM)

(AM)

April 24

2024_03

(AM)

(AM)

May 24

2024_04

(AM)

(AM)

June 24

2024_05

(AM)

(PM)

July 24

2024_06

(PM)

(AM)

August

2024_07

(PM)

(AM)

September 24

2024_08

(PM)

(AM)

October 24*

2024_09

N/A

N/A

November 24

2024_11

(PM)

(AM)

December 24

No Release

No Release

No Release

January 25

2025_01

(PM)

(AM)

*additional time has been needed to complete the September 24 release items, therefore upgrades will proceed to the following month.